WA Schools Public Private Partnership Project

Report 11: 13 June, 2018

Introduction and Background

This audit assessed whether the WA Schools Public Private Partnership (PPP) Project is on track to deliver its intended benefits. We focused on the following questions: Is the project being … Read more →

Audit conclusion

Two-and-a-half years into the PPP contract, the build program is on track. So far, 4 primary schools and the first stage of a secondary school have opened on time, with … Read more →

Key findings

The PPP was supported by reasonable analysis and robust procurement The analysis in 2009 and 2010 supporting a Design, Build, Finance, Maintain PPP was reasonable. After considering DoE’s Strategic Asset … Read more →

Recommendations

1.    Contract management and training The DoE should by December 2018: a.    develop a contract management plan and other manuals for opening schools and managing the school operations phase of … Read more →