The Banksia Hill Detention Centre Redevelopment Project

Recommendations

  • DCS should strategically plan (short and long term) accommodation options for juvenile detainees.
  • BMW and its client agencies need to ensure that project governance, management and tendering approaches are appropriate to the overall risk profile for a project, and not just the apparent financial risk.
  • Where risks are identified on a project and risk management plans formulated, those holding governance responsibilities should ensure that the plans are implemented and risks are actively managed.
  • Agency staff should provide accurate and reliable information to Senior Management and the Minister so that appropriate decision making can occur.
  • BMW and its client agencies should ensure that project governance mechanisms, roles and responsibilities, including for maintaining project documentation, are clear and understood on capital works projects.