Horizon should:
- ensure it more fully discloses the full cost of PUPP.
The Department of Regional Development should:
- stringently maintain its requirement since July 2013 of RfR funding submissions being supported by comprehensive business cases and sufficient evidence of project feasibility in regard to cost and timelines.
The Pilbara Development Commission should:
- as part of its role on the PUPP steering committee, ensure that the Ministers for Regional Development and Energy receive all relevant updates on progress and project risk.