Report 14: 2017

Non-Clinical Services at Fiona Stanley Hospital

Appendix 2: FM service payments

Appendix 2

Notes:

The contract was originally structured into 3 stages:

  • Pre-operations – planned from August 2011 to December 2013. This stage included equipment procurement and installation, and non-clinical service development.
  • Transitional – planned from December 2013 to April 2014. The stage where the FM took over management of the hospital site and provided partial and full operational services. This stage was fully replaced by the delay and phased stage where the FM maintained the hospital site, tested equipment and systems and delivered partial non-clinical services from October 2014 as part of a phased hospital opening.
  • Full operations – planned for April 2014. The point when the hospital was originally intended to become fully operational.